Public Works Department's County Projects
Project and Planning Schedule for 2010
2010 Project Construction Schedule:
Inchelium Safe Routes to School
CRP 809
1.3 miles Pedestrian Trail
Funded by : State,Safe Routes to School programs
Dates :Construction may start as early as May, and depending on actual start date
could go as late as August.
The development and construction of 1.3 miles of an 8’ to 10’ wide asphalt pathway, located along the Inchelium Highway, Cut Off Road and Moccasin Road. To include but not limited to Pedestrian activated beacons, radar feedback signs, lighting, pavement markings and signs..
Bridge Creek safety:
CRP 901
M.P. 28.0 to 29.50
Funded by: Highway Safety Improvement Program (HSIP)
Dates: : Construction may start as early as June and depending on actual start date
could go as late as September.
The safety improvements of Bridge Creek Road No. 00020 from M.P. 28.0 to M.P. 29.5, work will include .25 HMA overlay 28’ wide, increased signage, shoulder & centerline rumble strips, paint striping, road side guidepost and guardrail as needed..
bridge Creek top east:
CRP 902
M.P. 10.29 to 17.4
Funded by: American Recovery and Reinvestment Act (ARRA)
Dates:Dates: Construction may start as early as June and depending on actual start date
could go as late as August.
The resurfacing of Bridge Creek Road No. 00020 from M.P. 10.29 to M.P. 17.4, work will consist of a Bituminous Surface Treatment..
Ferry County Low-Cost run-off road safety improvements:
CRP 903
Various Roads
Funded by:High Risk Rural Roads Program (HRRRP)
dates:Construction may start as early as June and depending on actual start date
could go as late as October.
Safety improvements of multiple roads in Ferry County, improvements to include, centerline and fog line stripping, road side guidepost and guardrail, as per attached exhibit A..
2011 Project Construction Schedule:
Bridge creek 4:
CRP 502
M.P. 17.4 to 20.4
Funded by:Rural Arterial Program (RAP)
Dates:Construction may start as early as May and depending on actual start date
could go as late as October.
Scope of project includes: reconstruction of 3.0 miles; by recycling existing pavement, adding cement to stabilize the base, adding CSTC for widening, paving with cold mix, adding BST surface and installing guardrail where needed..